top of page

2325 190 STREET, SURREY, BC

On behalf of Pure Industrial and Cedar Coast, Avison Young is excited to introduce the lease offering of Coastal Heights Distribution Centre, a premium 427,969 sf light industrial distribution facility located at 2325 190 Street, Surrey, BC.

A BEST-IN-CLASS

OFFERING

Coastal Heights Distribution Centre - Logo white & blue Border-01.png
Coastal Heights Distribution Centre - Lo

TAKING DISTRIBUTION TO NEW HEIGHTS

Coastal Heights Site Plan

FOOTPRINT: 425,869 SF
MEZZANINE: 2,100 SF

GROSS LEASABLE AREA: 427,969 SF

Coasytal Heights Rendering
Coastal Heights Distribution Centre - Lo

UNMATCHED

FEATURES

CLICK TO VIEW THE
COASTAL HEIGHTS VIDEO

________________________________
CONSTRUCTION
 
Insulated concrete tilt-up panels designed to the latest ASHRAE (energy code) standards


________________________________​
CEILING HEIGHT
 
36’ clear 


________________________________​
LOADING 


Dock doors: Forty-nine (49), 8’ x 10’

Grade doors: Two (2) drive-in doors with ramps, 12’ wide x 14’ high, with electric operated straight vertical lift 

Dock ramp grade: 1.0% (dock doors) and 6.0% (grade doors)

Levelers: 40,000 LB hydraulic levelers dock seals with bumpers

________________________________
LOADING COURTYARD
132.5’ loading courtyard
Fully screened


________________________________​
COLUMN GRID 

Typical 57’ by 38’-9” column grid
50’ deep staging bay


________________________________​
ELECTRICAL 

1,600 Amp three-phase service per building

________________________________​
SPRINKLER 
ESFR (NFPA 13) fire protection system

________________________________​
WAREHOUSE HEATING 
Gas fired, forced air unit heaters

________________________________​
WAREHOUSE HEATING 
Gas fired, forced air unit heaters

________________________________​
WAREHOUSE LIGHTING 

LED High-bay lighting 

________________________________​
FLOOR LOAD CAPACITY

8" slab 800 lbs/sf

________________________________​
PARKING 
455 parking stalls 


________________________________​
ZONING 
IB-1

base building completion
targeted Q1 2023 

Coasytal Heights Rendering
Coasytal Heights Rendering

TAKING DISTRIBUTION TO NEW HEIGHTS

CONSTRUCTION TIMELINE

TARGETED BASE BUILDING COMPLETION Q1 2023

Coastal Heights Distribution Centre - Lo

LIVE CAM FEEDS
Watch Now!
 

61214_3.jpg
Coastal Height Live Web Cams

JANUARY 8, 2022
Walls being tilted

SEPTEMBER 8, 2021
Slab being poured

Coast Heights Slab being poured
Coastal Heights Formworks

JULY 29, 2021
Formworks

JUNE 28, 2021
Site cleared

Coastal Heights Site Cleared
bottom of page